Construction Update 1/14/20

The carpet is being installed and the lights and ceiling are close to completion. We are getting excited for the final stages of the finishing for the Goppert Classroom Wing.

Construction Update 12/18/19

The hallways and classroom painting has been completed. 151 new lockers were installed and windows and doors were installed.

Construction Update 12/13/19

The hallways and classrooms are being painted, the finishing work is being completed and the floors are being finished. 

Construction Update 11/6/19

The walls and roof are up for the new classroom wing at SCA.

Construction Update 10/4/19

The walls are going up for the new classroom wing at SCA.

Construction Update 9/26/19

Concrete blocks and masonry is being completed now for the additional restrooms in the classroom wing.

Construction Update 9/19/2019

The steel beams have been installed and the steel trusses are being completed for the addition of the new classroom wing.

Construction Update 9/12/2019

The concrete has been poured and the steel beams are being added for the new classroom addition.

Construction Update 8/28/19

The rock is being poured to start the concrete slab for the new classroom addition.

Construction Update 8/21/19

The curbing for the new parking lot has been poured and the base of asphalt will be poured for the parking lot will be happening this week. 

Construction Update 8/14/19

Footings are being finalized as we prepare for steel to start going up the end of August.